Jobs analysed
312
stage completed in period
Avg baseline (all stages)
138 days
Avg actual (all stages)
152 days
+14 days vs baseline
Supervisors on or under baseline
1 of 12
all stages combined
Actual days between stages by supervisor
Cell = actual avg days (variance vs baseline). Green on/under, amber up to 20% over, red more than 20% over
SupervisorBase
base 21
Frame
base 28
Lockup
base 24
Fixing
base 35
Finishing
base 30
A. Rossi19 (-2)30 (+2)31 (+7)37 (+2)36 (+6)
B. Nguyen21 (0)31 (+3)33 (+9)34 (-1)38 (+8)
C. Patel24 (+3)36 (+8)28 (+4)33 (-2)34 (+4)
D. Walsh25 (+4)27 (-1)32 (+8)31 (-4)26 (-4)
E. Kim22 (+1)38 (+10)29 (+5)37 (+2)27 (-3)
F. Moore19 (-2)36 (+8)32 (+8)34 (-1)40 (+10)
G. Singh20 (-1)35 (+7)20 (-4)37 (+2)37 (+7)
H. Brown29 (+8)38 (+10)26 (+2)40 (+5)33 (+3)
I. Clarke17 (-4)29 (+1)28 (+4)38 (+3)37 (+7)
J. Lee18 (-3)34 (+6)25 (+1)31 (-4)28 (-2)
K. Evans28 (+7)37 (+9)21 (-3)32 (-3)38 (+8)
L. Scott31 (+10)24 (-4)27 (+3)33 (-2)34 (+4)
Selected stages: Frame to Lockup
Baseline vs actual days by supervisor
SupervisorBaselineActualVariance
A. Rossi52
61
+9
B. Nguyen52
64
+12
C. Patel52
64
+12
D. Walsh52
59
+7
E. Kim52
67
+15
F. Moore52
68
+16
G. Singh52
55
+3
H. Brown52
64
+12
I. Clarke52
57
+5
J. Lee52
59
+7
K. Evans52
58
+6
L. Scott52
51
-1